Municipal
Street Projects
|
Hall
Street
Webb
City, MO |
For Webb City, MO, TSE designed roadway improvements for approximately
1.4 miles of Hall Street. Hall Street is a north-south corridor
with traffic that includes industrial, educational and bypass
uses. The street was in significant disrepair. TSE’s design
solutions included two intersections and two vertical curves that
will be leveled out for improved sight distance. The entire length
will be milled and used in new pavement overlay. TSE also negotiated
right-of-way for the project with local citizens. This project
is currently under construction.
| Howard
Bush Drive
Neosho,
MO |
TSE
designed plans for the extension of Howard Bush Drive from the
Industrial Park north to Rte. 60. This new roadway provides an
improved truck access point to Route 60 at a new signalized intersection
and eliminates a dangerous at-grade crossing with the Kansas City
Southern Railroad. This 3000’ long extension was funded
by a CDBG economic development grant and a MoDOT cost share agreement.
The extension was designed to minimize impacts to an existing
16” D.I. pressure sewer along the corridor. The intersection
at Route 60 is currently under construction.
|

|
|
|